The panel has mixed views on Duke Energy's (DUK) 1,365 MW Anderson County NG plant. While some analysts highlight the regulatory clarity, local economic benefits, and efficient capacity addition, others raise concerns about pipeline constraints, potential stranded asset risk, and regulatory approval not being a 'free pass'.
Risk: Pipeline constraints and potential stranded asset risk
Opportunity: Regulatory protection and economic benefits
(RTTNews) - The Public Service Commission of South Carolina (PSCSC) has approved Duke Energy's plans to build a new natural gas generation facility in Anderson County.
According to a survey conducted by Ernst & Young, the project is expected to support more than 2,200 jobs annually during the multi-year construction phase, including 746 construction jobs in Anderson County. Once operational, the facility is projected to generate an annual statewide economic impact of $84 million, supporting 125 jobs and $10 million in annual labor income.
The plant will be one of the most efficient natural gas facilities in Duke Energy's system. It will feature advanced environmental control technologies designed to minimize emissions, use 90% less water compared to traditional wet cooling methods, eliminate the need for chemical water treatment, and avoid producing a vapor plume. Additionally, the facility is expected to have a longer lifespan than previous natural gas technologies.
Ownership of the plant's approximate 1,365 MW nominal capacity will be shared, with Central Electric Power Cooperative holding 95 MW and North Carolina Electric Membership Corporation holding 100 MW.
Construction is scheduled to begin in the summer of 2027, with the facility expected to begin serving customers by early 2031.
The views and opinions expressed herein are the views and opinions of the author and do not necessarily reflect those of Nasdaq, Inc.
AI Talk Show
Four leading AI models discuss this article
"Regulatory approval de-risks the project, but capex magnitude, cost-recovery terms, and long-term merchant economics remain opaque and will determine whether this accretive or dilutive to shareholder returns."
Duke Energy (DUK) gets regulatory clarity on a 1,365 MW baseload asset with 95-100 MW committed to cooperatives, reducing merchant risk. The 2031 in-service date fits Duke's decarbonization timeline—natural gas as transition fuel, not stranded asset. However, the article omits capex. A 1.3 GW modern CCGT typically costs $1.2–1.8B; Duke's cost-recovery mechanism and rate base treatment are unstated. If regulators cap returns or delay cost recovery, this becomes a drag on ROIC. The 2027 start is also 2.5 years out—regulatory risk, supply chain, labor costs could all shift materially.
Natural gas plants face accelerating stranded-asset risk as renewables + storage economics improve; a 2031 asset with 30+ year life faces existential pressure from decarbonization mandates and carbon pricing that could render it uneconomic mid-life.
"The decade-long lead time for this project risks rendering its technology and cost-structure obsolete before the first megawatt is delivered."
This approval is a strategic win for Duke Energy (DUK), securing a 1,365 MW baseload capacity expansion to meet the Southeast’s surging industrial demand. The 90% water reduction and lack of vapor plumes mitigate local environmental pushback, while the shared ownership model with cooperatives spreads the capital expenditure (CapEx) burden. However, the 2031 operational target is a lifetime away in energy markets. By then, the levelized cost of energy (LCOE) for renewables plus long-duration storage may undercut gas, potentially turning this 'efficient' plant into a stranded asset before it even fires its first turbine.
The four-year gap before construction even begins leaves this project highly vulnerable to shifting federal EPA regulations on carbon capture for gas plants, which could balloon costs. Furthermore, if natural gas prices revert to historical volatility, the 'economic impact' touted here could be erased by fuel-cost pass-throughs to disgruntled ratepayers.
"Commission approval for a 1,365 MW gas plant increases Duke’s regulated capital exposure but creates a long-lived fossil asset at risk from falling storage+renewables costs, future carbon/methane regulation, and execution/cost overruns."
This project locks Duke Energy (DUK) into a large, long-dated natural gas asset (≈1,365 MW) with construction only starting in 2027 and commercial operation in early 2031. Near-term positives: local jobs, lower water use, and emissions controls ease permitting and PR. But absent cost figures, the plant could materially expand Duke’s regulated rate base and capital spending needs just as storage+renewables are becoming cheaper and decarbonization policies (or methane regulation) could raise fuel or compliance costs. Timeline risk, supply/pipeline constraints, capex inflation, and potential legal/ESG challenges are underplayed in the article.
If South Carolina regulators allow cost recovery in rates, Duke can de-risk returns and the plant provides firm capacity that supports reliability as coal retires. Also, advanced tech and much lower water use materially reduce community opposition and operating costs versus older gas plants.
"PSC approval advances DUK's rate base expansion with 1,365MW of efficient, low-water NG capacity to ensure grid reliability through 2031."
PSC approval de-risks Duke Energy's (DUK) 1,365MW Anderson County NG plant, a cornerstone of its SC Integrated Resource Plan, adding efficient capacity (90% less water, advanced emissions controls) to meet rising demand reliably by 2031. Ernst & Young's projections highlight $84M annual economic impact and 2,200 construction jobs, bolstering DUK's rate base growth in a regulated market yielding 9-10% ROE. Shared ownership (195MW to co-ops) mitigates risk. Long 4-year build exposes to cost inflation, but positions DUK ahead of peak demand. Others may overlook how this counters intermittent renewables' variability.
A 2031 NG plant risks stranded assets amid Biden-era clean energy mandates, IRA incentives for solar/storage, and potential carbon pricing, rendering its 'efficiency' moot if retired early.
"Pipeline infrastructure, not EPA carbon rules, is the binding constraint for SC gas-plant viability by 2031."
ChatGPT flags pipeline constraints—critical omission. Duke's SC footprint already relies on Transco and Dominion pipelines; a 1,365 MW plant needs ~500 MMBtu/day. Gemini's carbon-capture EPA risk is speculative; the real near-term chokepoint is gas availability. If pipeline capacity is already allocated or requires $200M+ in infrastructure, that capex doesn't appear in Duke's estimates. This could push 2031 online date further right or force higher fuel costs via spot purchases.
"Regulatory capture in South Carolina likely shifts the risk of stranded gas assets from Duke Energy shareholders to the ratepayers."
Claude and ChatGPT highlight pipeline and capex risks, but everyone is overestimating the 'stranded asset' threat. South Carolina’s regulatory environment is historically protective; if the PSC approved this 1,365 MW build, they’ve likely signaled that ratepayers, not shareholders, will bear the cost of any premature retirement. The real risk isn't carbon pricing—it's the opportunity cost. DUK is locking up billions in a 2031 asset while competitors might use modular storage to capture peak pricing sooner.
"Regulatory approval does not guarantee full cost recovery—prudency reviews can force shareholders to bear overruns."
Gemini: regulatory approval isn't a free pass. States routinely perform prudency reviews during or after construction and can disallow recovery for imprudent overruns, flawed need forecasts, or poor contracting. With a 2027–2031 build horizon amid capex inflation and supply/pipeline risk, Duke faces realistic chances of partial disallowances, higher financing costs, or mandated rate credits—meaning shareholders, not ratepayers, could ultimately absorb significant losses despite the PSC nod.
"SC PSC approval and CWIP recovery mechanisms protect Duke's ROE from capex overrun risks highlighted by ChatGPT."
ChatGPT dismisses regulatory protection too hastily—SC PSC's upfront approval in Duke's IRP creates a strong prudency presumption, with CWIP (construction-work-in-progress) rate recovery during the 2027-2031 build shielding ROE from overruns. Gas plants rarely face disallowances unlike nukes (e.g., VC Summer). Panel overlooks how $84M annual economic impact from E&Y justifies rates, bolstering case for full recovery amid demand surge.
Panel Verdict
No ConsensusThe panel has mixed views on Duke Energy's (DUK) 1,365 MW Anderson County NG plant. While some analysts highlight the regulatory clarity, local economic benefits, and efficient capacity addition, others raise concerns about pipeline constraints, potential stranded asset risk, and regulatory approval not being a 'free pass'.
Regulatory protection and economic benefits
Pipeline constraints and potential stranded asset risk